19 ақпан 2022 ж.

Bumbești-Jiu: Publication of tender for purchase of 3 electric buses (8m) through the Regional Operational Program, Priority Axis 4 of the REGIO Program 2014-2020.
30.06.2022: contract was signed with Anadolu Automobil ROM (romanian importator for Anadolu Isuzu).
07.06.2023: all electric buses were delivered.

28 қазан 2021 ж.

Rovinari: Publication of tender for purchase of 3 electric buses (8m) through the Regional Operational Program, Priority Axis 4 of the REGIO Program 2014-2020.
18.01.2022: contract was signed with Anadolu Automobil ROM (romanian importator for SOR Libchavy).
12.2022: all electric buses were delivered.

24 қыркүйек 2021 ж.

Târgu Jiu: Publication of tender for purchase 15 trolleybuses (6 classic and 9 with batterries) (12m) through the Regional Operational Program, Priority Axis 4 of the REGIO Program 2014-2020.
17.02.2022: contract was signed with Solaris Bus & Coach.
10.06.2023: all trolleybuses were delivered.

10 наурыз 2021 ж.

Târgu Jiu: Publication of tender for purchase 9 trolleybuses with batteries (12m) through the Ministry of Regional Development and Public Administration.
09.08.2021: contract was signed with Solaris Bus & Coach.
01.2023: all trolleybuses were delivered (Târgu-Jiu 1627 — Târgu-Jiu 1635).

11 қыркүйек 2020 ж.

Târgu Jiu: Publication of tender for purchase 11 trolleybuses (12m) through the Ministry of Regional Development and Public Administration.
19.01.2021: contract was signed with Solaris Bus & Coach.
22.11.2021: all trolleybuses were delivered (Târgu-Jiu 1616 — Târgu-Jiu 1626).

1 желтоқсан 1999 ж.

Opening of the junctional interurban trolleybus track to Bârsești Romcim terminus (3.8 km) for line 2.

20 маусым 1995 ж.

Start of trolleybus operation in Târgu Jiu between Cartierul 9 Mai and Artego terminus (8.9 km) with line 1.