15 februarie 2025 an

Luoyang trolleybus route 102 stops running from February 15.

Noiembrie 2023 an

Trolleybuses no longer use contact network outside of the depot, traveling the full length of routes 101, 102 on battery power.

Iunie 2023 an

Trolleybus contact network east of Qilihe for route 103 is dismantled.

26 decembrie 2021 an

Metro line 2 opens between Erqiao Road and Balitang stations.

Septembrie 1984 an

Luoyang trolleybus stage 1 commences operation, with a total overhead wire length of 15.65㎞, 3 transformers, 4 turning loops and 1 depot. The route is operated by 40 thyorister controlled articulated trolleybuses.

Iunie 1983 an

Construction of Luoyang trolleybus stage 1 commences, undertaken by Henan Third Construction corps (depot), State Grid (wiring), PLA Unit 80590 (poles), Beijing Trolleybus Subdivision (overhead wires and transformers).