19 február 2022 .

Bumbești-Jiu: Publication of tender for purchase of 3 electric buses (8m) through the Regional Operational Program, Priority Axis 4 of the REGIO Program 2014-2020.
30.06.2022: contract was signed with Anadolu Automobil ROM (romanian importator for Anadolu Isuzu).
07.06.2023: all electric buses were delivered.

28 október 2021 .

Rovinari: Publication of tender for purchase of 3 electric buses (8m) through the Regional Operational Program, Priority Axis 4 of the REGIO Program 2014-2020.
18.01.2022: contract was signed with Anadolu Automobil ROM (romanian importator for SOR Libchavy).
12.2022: all electric buses were delivered.

24 szeptember 2021 .

Târgu Jiu: Publication of tender for purchase 15 trolleybuses (6 classic and 9 with batterries) (12m) through the Regional Operational Program, Priority Axis 4 of the REGIO Program 2014-2020.
17.02.2022: contract was signed with Solaris Bus & Coach.
10.06.2023: all trolleybuses were delivered.

10 március 2021 .

Târgu Jiu: Publication of tender for purchase 9 trolleybuses with batteries (12m) through the Ministry of Regional Development and Public Administration.
09.08.2021: contract was signed with Solaris Bus & Coach.
01.2023: all trolleybuses were delivered (Târgu-Jiu 1627 — Târgu-Jiu 1635).

11 szeptember 2020 .

Târgu Jiu: Publication of tender for purchase 11 trolleybuses (12m) through the Ministry of Regional Development and Public Administration.
19.01.2021: contract was signed with Solaris Bus & Coach.
22.11.2021: all trolleybuses were delivered (Târgu-Jiu 1616 — Târgu-Jiu 1626).

1 december 1999 .

Opening of the junctional interurban trolleybus track to Bârsești Romcim terminus (3.8 km) for line 2.

20 június 1995 .

Start of trolleybus operation in Târgu Jiu between Cartierul 9 Mai and Artego terminus (8.9 km) with line 1.